This $3,691,025 project was awarded to Michigan Paving and Materials Company. The construction schedule will begin Sept. 8,2014.

The contractor will mill approximately 2” of the existing asphalt surface off and then replace with Hot Mix Asphalt (HMA). The milling operation utilizes a milling machine that uses a rotating drum to remove and grind the road surface and utilizes a conveyor system to load waiting trucks.

This process is noisy and typically lasts for one day. Check here for updates.